we are providing coordination drawings for renovation construction projects.  the process requires us to measure and 3d model the existing MEP items, then model the new systems. these will attach to the existing systems.  how does one "lock" the existing systems so that when we are modeling and moving the new systems we don't move the existing systems.

Make sure that the existing systems have unique names and layers.  That is, they should not be the same as your new systems.  Then just lock the layer.  It will keep the mep items from moving.

*Expert Elite*
Keith.Brown
Posts: 1,233
Registered: ‎03-13-2008
Message 2 of 2 (289 Views)

Re: locking elevations

08-01-2012 04:28 PM in reply to: JEFFGREEN9043

Make sure that the existing systems have unique names and layers.  That is, they should not be the same as your new systems.  Then just lock the layer.  It will keep the mep items from moving.


Keith Brown AutoCAD MEP BLOG | RSS Feed
AutoCAD MEP 2014 | Revit 2014 | EastCoast CAD/CAM V6.1 | Visual Studio 2013
────────────────────────────────────
⁞|⁞ Please use Mark Solutions!.Accept as Solution and Give Kudos!Give Kudos as appropriate. Thank you!
Post to the Community

Have questions about Autodesk products? Ask the community.

New Post
Need installation help?

Start with some of our most frequented solutions to get help installing your software.

New AutoCAD MEP Category!

The AutoCAD MEP forum has moved into it's very own category page, and can no longer be found within the Additional Product Forums.

Announcements
Do you have 60 seconds to spare? The Autodesk Community Team is revamping our site ranking system and we want your feedback! Please click here to launch the 5 question survey. As always your input is greatly appreciated.