For example.
If I have added group of points on the surface and then add breaklines,the group of points will be behind in the order of priority.
I would like to indicate the group of points(or other elements) is always in the first position while adding new elements to the surface.
You don't need a wish for this one... It's in there. Go to Surface Properties>Definition [Tab]>Operation Type [Section]. From there you can reorder your surface operations.
example.
I add:
group of points "_ all points"
order of priority:
1) set of points "_ all points"
If you then add a breakline, the priorities will be:
1) set to breaklines1
2) point group "_ all points"
If you later add another breakline, the priorities will be:
1) set to breaklines2
2) Set to breaklines1
3) point group "_ all points"
What I want is that while adding new elements, can set an item in the first position, in this case the set of points, so that the result would be:
1) set of points "_ all points (FIXED)
2) Se to breaklines2
3) Set to breaklines1
I second this request. Personally I would always want the following order as a default:
1) All breaklines
2) All contours
3) All points
4) All boundaries
5) All surface smoothing
6) All surface pasting
I'm getting tired of having to adjust the order of my surface draws every time I add a breakline - having to shift it up above the smoothing and boundaries, for each and every new add. I'd love to keep boundaries/smoothing/pasting at the end automatically.