which field in quantity takeoff manager .csv file is for unit price?

2 REPLIES 2
Reply
Message 1 of 3
Kevin_Gagne
386 Views, 2 Replies

which field in quantity takeoff manager .csv file is for unit price?

I've successfully setup Quantity Takeoff using item numbers, item name and unit; as well as formulas to get the output I want from my codes. The only question I have: is there a field for input of the unit price so a summary report will also output cost?
2 REPLIES 2
Message 2 of 3
matt.wright
in reply to: Kevin_Gagne

I think you have to port it over to excel. Is that what you ended up doing?

 

Matt Wright. E.I.T.

TDH Engineering

Spokane WA

Matthew Wright, PE
TD&H Engineering
Message 3 of 3
BrianHailey
in reply to: Kevin_Gagne

QTO is Quantity Take Off and it does just that, tells you how much you have of something. It does absolutely nothing with cost. As Matt suggested, take the results into Excel to do the costs.

Brian J. Hailey, P.E.



GEI Consultants
My Civil 3D Blog

Can't find what you're looking for? Ask the community or share your knowledge.

Post to forums  

Rail Community


Autodesk Design & Make Report