Please see drawing attached.
I have a large fill area directly dropping to to a large cut area. All of the above work is in rock, There is a retaining wall along a section of the "cliff face" but not at the ends where the cut and fill meet.
I would like to transition the fill batter on to the cut batter to enable the filled area above to be self supporting.
How is it done please?
Thanks in advance
Sean
The bottom of wall breakline is incomplete. Add a new breakline as per the attached.
John Mayo