I have drawn a pipe network for a sanitary sewer line and i wanna adjust the flowline elevation of the entire system to match that of an existing manhole that i am connecting to. how do i adjust the entire system as a whole rather than individually adjusting each pipe section and structure?
old thread I know but since it is here and in the first that comes up in my search I think it is also worth noting that you don't want to grab and move the entire network, only the pipes.
I had a datum change on a project and thought it would recognice my surface shift...it does not.