Im a little embarassed to ask this question at this point but Im puzzed as to how to get the material quatity for leveling. I tried adding a pavament structure assinging level to the subbase (it does not offer level in the pavement structure) and I get what appears to be a milling qty. How do you get the T&L?
Solved! Go to Solution.
Solved by Joe-Bouza. Go to Solution.
As a work aroung I lowered FG the depth of overlay computed C&F for that vs eg and used the fill qty. The corridor should spit it out.