I need to calculate excavation volumes that have varying depths, a -1 foot
excavation line, -2, -5, -10 up to -30 lines. What is the best way to do
this? This site is NOT flat and very large. Probably hundreds of
thounsands of cubic yards of dirt. What is the best way to do this? For
one section I did this.
1-Copy existing grade
2-use the -1 excavation area as the boundary
3-moved it down one foot.
4-Merge with existing grade to created FG.
This results in a cliff type of formation, how do I smooth out this ridge?
Create a feature line at the -1 excavation contour and grade to existing
ground?
Any help with methods to calcuate this would be greatly appriecated!