Corridor Section Points Report

When creating a Corridor Section Points Report using the Toolspace>Toolbox>Reports Manager in Civil 3D 2012, the stations get listed but only a few contain point information (see attached).  I am trying to generate stake-out data for a proposed road.  I was able to get this report to work successfully in one of the Civil 3D tutorials, so I assume that nothing is wrong with the utility.  The problem may be related to my corridor.  Any help would be much appreciated.

6 REPLIES 6
Message 2 of 7
wfberry
in reply to: mtf20

I am not sure exactly what you are trying to do.  You don't need points exported to a Data Collector?

 

Bill

 

Message 3 of 7
GZE
Advocate
in reply to: mtf20

I have a simmilar problem did you find a solution for this?

Humphrey GZE
Civil 3D 2013 64bit SP1
Elitebook 8540w
Core i7 2.8GHz, 8Gig RAM
NVIDIA Quadro FX880
160Gb SSD
Message 4 of 7
adolyep
in reply to: mtf20

It Happens to me with my Sections. So a Solution I found was.

-Make the report into a Excel file and filter all the CHAINAGE Stations in a way that you can copy/paste only CHAINAGE Stations.

-Clean all CHAINAGE word (With replace into Excel)

-Clean all Plus Mark (You will have Numerical Stations only).

 

again into C3D,

-In the corridor properties>Parameters Tab> click on (...)Frecuency Button.

-A Frecuency to Apply Assemblies Window will appear, Click on the (+) button and you will be able to add stations.

-In the command bar paste the Numerical Stations you fixed.

-Rebuil the corridor and do the Report Again...

-Your Samples will be there.

 

Nevertheless. It Work well with most my alignements, but when I have Station Equation , even if the station appear in the model, it doesn't show in the report.

Message 5 of 7
Pointdump
in reply to: mtf20

mtf20,

 

You'll need to create the stake-out points before you can make a report of same.

Here's where I'd start:

 

COGO_Pts.png


Dave

Dave Stoll
Las Vegas, Nevada

EESignature

64GB DDR4 2400MHz ECC SoDIMM / 1TB SSD
NVIDIA Quadro P5000 16GB
Windows 10 Pro 64 / Civil 3D 2024
Message 6 of 7
BANI_INDICA
in reply to: Pointdump

yes the corridor beginning station is the point ... if you applied the frequency interval 5 the corridor considers every 5m interval from the beginning station which would lacking the information for the corridor section view report  where as the corridor section report considers at every 5m distance but not from the beginning station value !

Message 7 of 7
anthony.nr
in reply to: mtf20

Hi,

please go to corridor properties & in parameters change the frequency (lesser) & try to generate the report.

thanks,
Anthony
Civil 3D 2011, 64bit
Dell t1600 Win7 Pro.
Xeon 3.3GHz
8GB RAM

Can't find what you're looking for? Ask the community or share your knowledge.

Post to forums  

Rail Community


 

Autodesk Design & Make Report