I have an existing ground surface with all different z co-ords and im trying to add three proposed buildings to my exisiting ground with all the builidngs having a level of 32.5 as a minimum, however at some points the ground is higher than 32.5 and I only want to raise my existing ground to 32.5 within the proposed buidling layout if it is below 32.5 as im doing a flood calculation. What do i need to for this? Thanks.
Hi,
I would do the following steps:
HTH, - alfred -
Changing existing ground is a sure way to make any grading problem go away
Surley I jest, but typicaly we don'r change existing ground we build on it and cut into it - two different models. Then they can be combined.
Your Name
Did you find this post helpful? Feel free to Like this post.
Did your question get successfully answered? Then click on the ACCEPT SOLUTION button.
Your Name