2 Kudos
david.rust

Change Order Routing 'Gates'

Status: Under Review
by david.rust on ‎11-12-2013 08:35 AM

It would be useful if the Change Order process was more configurable.  Ie. Be able to remove some of the gates in the process.  For example, before we get to the work stage we have to ‘submit’ the change order twice (to Open etc), or we’d like to remove the ‘Checked stage’ for some of our Document categories.  This is pretty tiresome that we cannot configur.

Status: Under Review
Comments
by Active Contributor Gene.R on ‎01-23-2014 10:13 AM

I agree that the workflows should be configurable. I currently utilize 4 different change order scenarios. On some I would remove some of the states, others i would add additional states. I would also like to use alias names for the states so that open= CAD and work=ERP.

by Employee olearya on ‎02-13-2014 02:58 PM
Status changed to: Under Review
 

You are not logged in.

Log into access your profile, ask and answer questions, share ideas and more. Haven't signed up yet? Register

Announcements
IdeaStation Guidelines
Review guidelines and best practices
before posting a new idea
Top Kudoed Authors
User Kudos Count
17
17
13
11
10