Guidelines for Fill time of painted plastic parts

143 Views, 0 Replies
08-22-2012 08:06 AM

Hello,

 

I'm writing today to see if anyone can help with guidelines for gate sizing of plastic parts that will be painted post-molding. I remember during my training and professional experience that you need to fill plastic parts that will be painted later more slowly than normal. I was always told that a maximum bulk shear rate of 15,000s-1 was the preferred limit for such a case (painting or plating). However, I have never seen any publications/liturature to support or disprove this threshold.

 

I'm sure like all things there are different levels for different materials, but I'm wondering what other use for a guideline.

 

Any thoughts out there?

 

Thanks,

Erik

 