Hello,
We have an upcoming MEP project & will be working with another engineering
firm from out of town. As I understand it we will be working on six (6) floors
and the other firm will be working on three (3) floors.
Has anybody been in this situation before?...How will we & they connect
to ductwork/pipes etc. What's the best way of approaching this?
Any ideas would be greatly appreciated.
I've not been in such a situation, but be aware that one cannot connect elements or systems between a host model and a linked model. One method of coordination would be to use Copy/Monitor (which is imperfect). Below is a link to a thread with more information on this matter.