I have a linked Revit file in a project that has some casework I need to tag and put on a schedule. The casework tagged fine but it does not show up in the schedule? I have it set on a Multi-Category schedule, and all the other tags that aren't in the linked file are showing up fine on the schedule.. Any ideas?

2 REPLIES 2
Message 2 of 3
constantin.stroescu
in reply to: Anonymous

Have you checked the Include Elements in Linked Files from Schedule Properties....?

Image 1.png

Constantin Stroescu

EESignature

Message 3 of 3
Anonymous
in reply to: constantin.stroescu

Holy Red Robin Batman it worked! THANK YOU! Its amazing how easily things get overlooked in this program haha.