Hi All,
Can someone please advise re: Revit phasing.
Context: Existing walls upgraded to New Construction
When upgrading
an existing wall to
a new construction wall do we either :
1. edit the wall type and call it New Construction
(but this means the existing wall disappears altogether and we lose all record of the Existing phase),
OR
2. draw the wall again in the same place as New (but this creates problems of wall overlapping, etc) ?
In short: do we lose the Existing building data and all associated views as soon as we edit walls, floors etc to become New construction?
Existing building and views can be kept if they are separate walls, etc but not if it is essentially the same wall, but upgraded?
I can't get the answer to this in the Revit Manual or anywhere else.