Hello,
i guess i have 2 questions
We create lots of nwd files from pdms thru rvm export and convert the rvm to nwd and we also have a nwp file stored on the server. But when i open the nwd file the first time i allways have to attach the nwp file first by hand.
I would like to know if there's a way to tell navisworks to add allways a nwp file when i open a new converted nwd file the first time.
and the second thing would be then to run the presenter rule created to add the materials to the items.
So the whole steps i would like to have automated
----
1 open nwd file
2 add according nwp file
3 run the presenter rule
-----
Would save us lots of time if we would have something like that automated.
br
Christian
You might be able to do with this with iConstruct BIM Flow. The NWP file is what I am not sure about. Reach out to iConstruct service.desk@iconstruct.com and ask them.