Navisworks General

Reply
Active Member
Posts: 7
Registered: ‎07-17-2012
Message 1 of 5 (910 Views)

Navisworks 2013 crashes when linking Primavera P6 in timeliner

910 Views, 4 Replies
07-17-2012 04:07 AM

Hi,

    I have just set up a Primavera DSN data source to add directly to Navisworks timeliner however when I add the DNS and click OK Navisworks unexpectly crashes everytime instead of giving me the option of selecting a project. Windows message just states "Navisworks has stopped working" see attached error message. Both programs have been recently installed and run OK, files are small. Does anyone know how to approach this problem?

Member
IMHAWLEY
Posts: 3
Registered: ‎07-04-2011
Message 2 of 5 (902 Views)

Re: Navisworks 2013 crashes when linking Primavera P6 in timeliner

07-18-2012 12:36 AM in reply to: TROY001

Hi There Could you tell me more about your installation, such as whether you're 32 or 64 bit, which OS, which version of the P6 SDK you are using?

 

Thanks a lot

Ian Hawley

Navisworks, TimeLiner Lead

Active Member
Posts: 7
Registered: ‎07-17-2012
Message 3 of 5 (892 Views)

Re: Navisworks 2013 crashes when linking Primavera P6 in timeliner

07-19-2012 08:02 AM in reply to: IMHAWLEY

Hi Ian,

          its Windows Vista Home 32 bit operating system and Ive installed Primavera version P6.0 + associative SDK component, thank you

 

FYI; In the meantime I was sucessful in exporting my Primavera project to Microsoft Office Project and linking to Navisworks timeliner - not sure if this info helps, thanx

Member
IMHAWLEY
Posts: 3
Registered: ‎07-04-2011
Message 4 of 5 (888 Views)

Re: Navisworks 2013 crashes when linking Primavera P6 in timeliner

07-19-2012 08:09 AM in reply to: TROY001

Hi There

 

If you are on P6.0 we would recommend you upgrade to 6.2 as this is our minimum supported version.

 

If you are able to use the Web Services connection, I highly recommend this as our testing has proved updates to be in the region of 10-100 times quicker.

 

Kind Regards

Ian Hawley

Navisworks, TimeLiner Feature Lead

Active Member
Posts: 7
Registered: ‎07-17-2012
Message 5 of 5 (881 Views)

Re: Navisworks 2013 crashes when linking Primavera P6 in timeliner

07-19-2012 06:37 PM in reply to: IMHAWLEY
Will do, thanks Ian

You are not logged in.

Log into access your profile, ask and answer questions, share ideas and more. Haven't signed up yet? Register

Announcements
Have API Questions?
New Dedicated Forum for Navisworks API

Need installation help?

Start with some of our most frequented solutions to get help installing your software.

Ask the Community