Revit to Timeliner

I new to Navisworks and am trying to learn how to import and 4D simulate revit files.  I created a basic revit mdel (footings, foundation walls, floor slab, brick on CMU exterior walls - the concrete in the footings has a unique material name from the concrete in foundation wall, as does the slab concrete).  I opened Timeliner added a task with start and end dates, then used the attach button to attach geometry (ie footings) to that task. After assigning geometry to tasks I ran simulation and nothing happens (blank).  What steps am missing here? Suggestions?

1 REPLY 1
Message 2 of 2
jeang
in reply to: Stan6287

Have you made sure you assigned a "Task Type"? THis controls the visibilty of the object when the activity is played (Construction activity, Temporary activity or Demo).

 

It an extra column in Timeliner. The Configuration tab lets you customize the looks.

Autodesk Autocad 2013 Certified Professional
Autodesk Revit 2013 Certified Profesional
Autodesk Civil 3D 2013 Certified Professional

Can't find what you're looking for? Ask the community or share your knowledge.

Post to forums  

Rail Community


 

Autodesk Design & Make Report