I've exported my schedule from P6 as a .mpx successfully with no errors. I try to create a link in Navisworks Timeliner, but none of the activities show up. I've performed this process successfully with other projects that were exported from P3, but I am having trouble with files that I export from P6. Anyone have an idea why this might be happening? Thanks in advance!
Can you add the tag
60,id,unique id,name,start,finish,duration,% complete,% work complete,actual cost,actual duration,actual start,actual finish,actual work,baseline cost,constraint type,constraint date,cost,cost2,cost3,cost variance,critical,duration1,duration2,duration3,early finish,early start,fixed,fixed cost,flag1,flag2,free slack,hide bar,late finish,late start,milestone,notes,number4,number5,outline level,predecessors,priority,successors,text1,text2,text3,text4,text5,text6,text7,text8,text9,text10,total slack,unique id predecessors,unique id successors,WBS
betwen the line 57 and 61...
Marcio Dias
Hi there,
What version of Navisworks & P6 are you using? Is there a reason why you're exporting to MPX rather than using the TimeLiner data source specifically for P6 (via Web Services)? We would strongly recommend using the native support for the project data source rather than MPX.
Thanks,
Jeff
Microsoft Project no longer supports export to the MPX format (since 2000?). How can one link Timeliner to a Project schedule?