Change Orders - Markup - Workflow Question

Change Orders - Markup - Workflow Question

mthomas
Collaborator Collaborator
826 Views
2 Replies
Message 1 of 3

Change Orders - Markup - Workflow Question

mthomas
Collaborator
Collaborator

I'll try my best to explain the situation... say I've created a markup (DWF) within a change order and the markup containsh multiple notes / leaders / etc. I've saved the markup, which has generated a comment... so far so good.

 

Now I have realized that I did not want one of the annotations in the markup. The problem seems that there is no method to the dwf markup to remove the annotation and save the DWF and updating / creating a new comment

 

If I add an annotation to an existing markup and click save it will prompt me to save a new markup and it creates a new comment.... as I would expect.... But I can NOT delete anything

.

I can checkout the markup and make changes but this does NOT create a new comment or update the DWF markup contained in the intial comment.

 

Suggestions?

Mike Thomas

Accepted solutions (1)
827 Views
2 Replies
Replies (2)
Message 2 of 3

olearya
Alumni
Alumni
Accepted solution

Hey Mike,

 

If you open this in ADR you should be able to go to the "markups" tab, unlock the annotation / markup object and delete it.  

 

Now - this does not take care of automatically saving to Vault and updating CO attachments, you will have to do this manually.



Allan
Product Manager
Autodesk, Inc.
0 Likes
Message 3 of 3

mthomas
Collaborator
Collaborator

that's what I figured, just found it odd that there wasn't a workflow for this built-in

Mike Thomas