Is anyone relying solely on panel schedules in Revit for medium to large commercial projects? I try to lock in circuit #s but still input my loads into our Microsoft Excel shedules. We want to depend fully on the Revit schedules but that creates some concerns:
You cannot typical anything - you have to lay out devices in every space and circuit it for proper loading
Connecting Mechanical to your panels when it is a linked file or they are using AutoCAD
Modeling and connecting existing to balance loads properly
If using light fixtures or other devices from manufacturers you must verify all load classifications and demands as well as occasionally add the electrical connectors and VA to use them in your project
Are these problems anyone is having or has overcome? We have the Revit schedules modified so they work appropriatley but there is no flexibility-if it is not circuted it is not calculated, so we are nervous to abandon our Excel schedules