    Demolished Rooms/Spaces

    306 Views, 8 Replies
    10-12-2011 06:23 AM

    Rooms and Spaces only have a "Phase Created" parameter so the new spaces show up on our demolition drawings, which are set to the New Construction phase, of course. We are looking for a way of showing the architect's room names/numbers on our demo drawings that's more efficient than creating an existing room view and overlaying it. Has anyone discovered a good method?

    Corey D.                                                                                                                                                               LogoEE.png   AutoCAD user  Revit user
    ───────────────────────────────────────────────────────────────────────────────────────────
    ⁞|⁞ Please use the Mark Solutions!.Accept as Solution and Give Kudos!Give Kudos functions as appropriate to further enhance the value of these forums. Thank you! ───────────────────────────────────────────────────────────────────────────────────────────
    Please use plain text.
    Member
    albim10
    Posts: 3
    Registered: ‎01-21-2011

    Re: Demolished Rooms/Spaces

    10-12-2011 01:08 PM in reply to: CADastrophe

    In Revit 2012 you can now tag architectural rooms through the linked architectural model into your views.  You can even do it with the "Tag All" tool.

     

    Hope this helps!

    Please use plain text.
    *Expert Elite*
    Posts: 1,912
    Registered: ‎08-28-2009

    Re: Demolished Rooms/Spaces

    10-12-2011 01:33 PM in reply to: albim10

    That's a good suggestion, however, the issue lies more with the phasing. If the link's phase is set to existing, we get the existing room names we're after, but we lose the demolished architecture.

    Corey D.                                                                                                                                                               LogoEE.png   AutoCAD user  Revit user
    ───────────────────────────────────────────────────────────────────────────────────────────
    ⁞|⁞ Please use the Mark Solutions!.Accept as Solution and Give Kudos!Give Kudos functions as appropriate to further enhance the value of these forums. Thank you! ───────────────────────────────────────────────────────────────────────────────────────────
    Please use plain text.
    Member
    albim10
    Posts: 3
    Registered: ‎01-21-2011

    Re: Demolished Rooms/Spaces

    10-12-2011 01:46 PM in reply to: CADastrophe

    Usually, after mapping ythe Phases from your model with the Phases from the linked arch model, everything should show properly in your views according to the Phase property assigned to your views.  You do this by accessing the type properties of the linked arch model then clicking on the Edit button on the Phase Mapping Parameter Value.  See attached image.

     

    Hope this helps!

    Please use plain text.
    *Expert Elite*
    Posts: 1,912
    Registered: ‎08-28-2009

    Re: Demolished Rooms/Spaces

    10-13-2011 05:20 AM in reply to: albim10

    Everything maps out and does appear properly - the only issue lies with the demolition views. The view's phase must be set to "New Contruction" with the Phase Filter set to "Show Previous + Demo" to show the demo info. Since the view's phase is set to New Construction, only the rooms on that phase show up, which are the new rooms. We want to show the rooms from the Existing phase on these demolition plans.

    Corey D.                                                                                                                                                               LogoEE.png   AutoCAD user  Revit user
    ───────────────────────────────────────────────────────────────────────────────────────────
    ⁞|⁞ Please use the Mark Solutions!.Accept as Solution and Give Kudos!Give Kudos functions as appropriate to further enhance the value of these forums. Thank you! ───────────────────────────────────────────────────────────────────────────────────────────
    Please use plain text.
    *Expert Elite*
    Posts: 1,912
    Registered: ‎08-28-2009

    Re: Demolished Rooms/Spaces

    12-01-2011 05:21 AM in reply to: CADastrophe

    Just looking to reiterate this question one more time since our solutions are, like many others, an absolute pain and terrible investment of time. Thanks.

    Corey D.                                                                                                                                                               LogoEE.png   AutoCAD user  Revit user
    ───────────────────────────────────────────────────────────────────────────────────────────
    ⁞|⁞ Please use the Mark Solutions!.Accept as Solution and Give Kudos!Give Kudos functions as appropriate to further enhance the value of these forums. Thank you! ───────────────────────────────────────────────────────────────────────────────────────────
    Please use plain text.
    Distinguished Mentor
    asommer
    Posts: 752
    Registered: ‎08-10-2009

    Re: Demolished Rooms/Spaces

    12-01-2011 06:39 AM in reply to: CADastrophe

    I know when I had a job with 3 "new construction" phases, I had to place spaces for 1st phase and copy them to 2nd and third phase.  you might have to place the demolition spaces in the demolition phase.

    Please use plain text.
    *Expert Elite*
    Posts: 1,912
    Registered: ‎08-28-2009

    Re: Demolished Rooms/Spaces

    12-01-2011 07:45 AM in reply to: asommer

    The Spaces are attributed to an Architectural Link and the spaces are in the demolition phase. Our Existing views are fine, but our Demo views have to be set to the New Construction Phase, which then eliminates the existing Spaces. Is anyone showing room numbers at all on their Demo drawings in Revit?

     

    Example of what I'm running into: Room 101 and Room 102 and being combined into Room 103 by demolishing a joining wall.

    The Spaces for 101 & 102 are placed under the Existing Phase, and Space for 103 is placed under the New Construction Phase. There is no parameter for Phase Demolished for Spaces or Rooms. In a demo view, I have to set the Phase to "New Construction" and Phase Filter to "Show Previous + Demo". Thus, the Space for the new Room 103 is showing up, not 101 and 102 like I want.

    Corey D.                                                                                                                                                               LogoEE.png   AutoCAD user  Revit user
    ───────────────────────────────────────────────────────────────────────────────────────────
    ⁞|⁞ Please use the Mark Solutions!.Accept as Solution and Give Kudos!Give Kudos functions as appropriate to further enhance the value of these forums. Thank you! ───────────────────────────────────────────────────────────────────────────────────────────
    Please use plain text.
    Distinguished Mentor
    asommer
    Posts: 752
    Registered: ‎08-10-2009

    Re: Demolished Rooms/Spaces

    12-01-2011 08:40 AM in reply to: CADastrophe

    Oh yeah, I forgot.  The architect has to place the rooms in each phase the same way you want to.  If you want to see the room name & number in demo phase, they need to place rooms in thier demo phase.