01-29-2013 10:36 AM
I've added the fields in my door schedule for head, jamb and sill details. These field appear be manually completed. Is there a way to link the field to the actual detail?
That way, for example if the detail were to be moved to another sheet, the field in the door schedule would be automatically updated.
Solved! Go to Solution.
Re: door schedule - keying in details
Options
- Mark as New
- Bookmark
- Subscribe
- Subscribe to RSS Feed
- Highlight
- Email to a Friend
- Report Inappropriate Content
01-31-2013 12:55 AM in reply to:
wpiotraschke
Unfortunately not. This is still a manual process I am afraid. It isn't possible to reference other views within a schedule.
Kevin Fielding
BIM Coordinator
AEW Architects
Manchester, UK
If my post solves your issue, please accept this as a solution and give me a thumbs up!