Hi..
We are trying to set up a template for our Sustainability calculations...
Essentially I was able to create required schedules with added parameters and calculate percentages for the total values etc...
But I am not sure if Revit would let me insert certain algebraic formulae....like
Glazing factor calcuation...
[ Window Area(SF) / Floor Area (SF) ] x Window Geometry x [ Actual T / Minimum T ] x Window Height factor...
The above is a basic formula with values few taken from the schedule and few constant...
What would be the best way to set this formula in Revit sothat it takes the values from the project shcedules and do the calculation
and give the result onto the Sheet View.
How do we handel general Sustainability Calcuations ? Should we use excel for calculations and key in the values into Text on our sheet ?
I hope you got the picture of what we are trying to acheive.... Any suggestions regarding this would be higly appreciated...
Thank you
Kesari
Syntec
We are trying to set up a template for our Sustainability calculations...
Essentially I was able to create required schedules with added parameters and calculate percentages for the total values etc...
But I am not sure if Revit would let me insert certain algebraic formulae....like
Glazing factor calcuation...
[ Window Area(SF) / Floor Area (SF) ] x Window Geometry x [ Actual T / Minimum T ] x Window Height factor...
The above is a basic formula with values few taken from the schedule and few constant...
What would be the best way to set this formula in Revit sothat it takes the values from the project shcedules and do the calculation
and give the result onto the Sheet View.
How do we handel general Sustainability Calcuations ? Should we use excel for calculations and key in the values into Text on our sheet ?
I hope you got the picture of what we are trying to acheive.... Any suggestions regarding this would be higly appreciated...
Thank you
Kesari
Syntec
Re: Please help... Setting up Formulae in Revit.
Options
- Mark as New
- Bookmark
- Subscribe
- Subscribe to RSS Feed
- Highlight
- Email to a Friend
- Report Inappropriate Content
06-01-2010 10:01 AM in reply to:
syntecgroup
Revit has a good capability for adding formulas to values in schedules. However, this is relatively simple when you need to do calculations within a certain type of schedule, such as a window schedule. It's not simple when you need to mix data from different types of entities, such as Windows and Floors, and other things. One possible solution is to extract data to Excel from separate schedules, and continue the calculations in the spreadsheet.
Or, you might be interested in looking at Autodesk Ecotect Analysis, at this link:
http://usa.autodesk.com/adsk/servlet/pc/index?site ID=123112&id=12602821
Alfredo Medina
info@planta1.com
http://www.planta1.com
Online Revit Training
Or, you might be interested in looking at Autodesk Ecotect Analysis, at this link:
http://usa.autodesk.com/adsk/servlet/pc/index?site