    Material volume show in simulation

    148 Views, 1 Replies
    11-16-2011 04:17 AM

    Can we show the material volume with navisworks time linear simulation in according to duration (daywise)

    Please use plain text.
    Product Support
    Posts: 476
    Registered: ‎10-02-2007

    Re: Material volume show in simulation

    11-23-2011 09:05 AM in reply to: RNDPIS

    Do you mean as in the actual volume of Material Excavated for example?

     

    It isn't possible to show this but you can go into the settings and Add the task name and percentage of the task complete, which you can show under the date

     

    Go to Overlay Text > Edit, select where you would like the Task name to go (Ctrl +Enter if on the next line) > Extras > Currently Active Tasks

     

    This is obviously a sample image model but hopefully you get the idea.

    timeliner.png