Hi,

I just want to understand  what is meaning of :"High intensity or high material flow path" as one of the Material flow  Analysis  result of ?

Another questions: if there is more than one Job ..is there any indicators to overlap between them during one Working Shift?

 

1 REPLY 1
Message 2 of 2
mike.jolicoeur
in reply to: Ehsancad

High intensity path is the path where it has the most traffic.  The traffic volume can be measured by three different criteria: number of parts, number of parts * travel distance, and transportation cost.

 

Currently we don’t support scheduling on material flow analysis for Working Shift. We assume all jobs happen at the same time. We will add this request to our backlog for future enhancements.