    Submittal Packages

    263 Views, 4 Replies
    06-08-2008 07:58 PM
    I'm curious to know how others are using submittal packages. Currently we are set up that we created a single package for each prime contractor to add their items to for review. Are others set up this way or are contractors creating new packages for each submission? I'd like to hear how you're working with this and why~

    Thanks!
    Please use plain text.
    Employee
    Posts: 13
    Registered: ‎06-04-2008

    Re: Submittal Packages

    06-09-2008 09:44 AM in reply to: hotpepr1
    That's perfect if the prime contractor is going to submit all their submittal items at the same time. In reality their subcontractors are going to submit their items to the prime contractor and then the prime contractor will forward those to get the items "off their desk".

    For example, I have seen when the HVAC contractor would send in 1/2 of his submittals on day and then 3 weeks later send in the "stragglers". Guess what, the engineer on the project "Rejected" the first package, so the GC had to go through the whole process again.

    I think the better way to set it up is to consider the following:
    1) Who is reviewing the submittal items which is usually the Architect / Engineer / Consultant? What items do they need in a "Package" in order to determine if the items meet the specifications.
    -- Lesson learned: Get the project team together before the first submittal is sent in to determine what "best practices" are going to be used on the project. Don't expect everyone will do it the same way because they won't.
    2) Another idea is to utilize a "Communication Specification" to tell everyone on the project how they are expected to do things such as submittals.
    3) Packages based on the "Bid Package".
    4) Packages based on the CSI Code such as:
    034100 - Precast Structural
    034500 - Precast Architectural Concrete
    034700 - Site-Cast Concrete
    etc.

    I also attached a submittal overview that one of the Autodesk Constructware Consultants put together to might help you understand submittals and ideas for structuring it for your project.

    Hope this helps.
    Jeff Marsh
    Jeff Marsh
    Technical Product Manager, Construction Business Line
    AEC Solutions Group

    Autodesk, Inc.
    Please use plain text.
    Active Contributor
    Posts: 26
    Registered: ‎03-01-2007

    Re: Submittal Packages

    06-09-2008 11:14 AM in reply to: hotpepr1
    Are there more of these articles posted somewhere??? Thanks for the article, it really breaks down the process and puts into "real" scenarios that make sense. I've come across a few other articles from time to time but had to search through the sites to find them. You are such a great help (and I'm so happy you read these boards!!!).
    Please use plain text.
    Employee
    Posts: 13
    Registered: ‎06-04-2008

    Re: Submittal Packages

    06-09-2008 11:45 AM in reply to: hotpepr1
    Nothing yet. The goal is to start posting this information on the "Knowledge Base" area. The support group is responsible for working on what is going to be housed there. I'll ping the manager and see if there is any update.
    Jeff Marsh
    Technical Product Manager, Construction Business Line
    AEC Solutions Group

    Autodesk, Inc.
    Please use plain text.
    Active Contributor
    Posts: 26
    Registered: ‎03-01-2007

    Re: Submittal Packages

    07-25-2008 07:34 AM in reply to: hotpepr1
    Jeff -
    Do you have any more of these great papers on Budgets in Constructware?? The submittals paper was very helpful! I can't wait for the Knowledge Base release!