Bill Of Materials

327 Views, 2 Replies
08-20-2012 06:54 AM

I just received instruction to run a BOM (Bill Of Materials) on an entire piping job.  Meaning, we want to extract a BOM that accounts for every line number we have in that job folder.  Is that possible to do?

*Expert Elite*
dave.wolfe
Posts: 654
Registered: ‎12-04-2009
Message 2 of 3 (323 Views)

Re: Bill Of Materials

08-20-2012 08:47 AM in reply to: jeremylegleu

Yes, you'll need to group your items according to the line number.  Use the report creator.  At the bottom of the page referred to in the link below there is a short section on grouping. Basically, you'll switch out the Short description field with the Line number tag field.

 

http://www.pdoteam.com/2012/07/creating-a-bill-of-material-row-number-in-plant-3d-reports/

Dave Wolfe
Isaiah 57:15

ECAD, Inc.
Tips and Tricks on our blog: Process Design, from the Outside

A P3D Authorized Reseller
Contributor
jeremylegleu
Posts: 14
Registered: ‎04-02-2012
Message 3 of 3 (318 Views)

Re: Bill Of Materials

08-20-2012 10:00 AM in reply to: dave.wolfe

Got it, thanks for your help!

You are not logged in.

Log into access your profile, ask and answer questions, share ideas and more. Haven't signed up yet? Register

Announcements
Are you familiar with the Autodesk Expert Elites? The Expert Elite program is made up of customers that help other customers by sharing knowledge and exemplifying an engaging style of collaboration. To learn more, please visit our Expert Elite website.

Need installation help?

Start with some of our most frequented solutions to get help installing your software.

New AutoCAD Plant 3D Category!

The AutoCAD Plant 3D forum has moved into it's very own category page, and can no longer be found within the Additional Product Forums.

Ask the Community