    Revision history for each drawing

    457 Views, 7 Replies
    11-28-2012 01:30 PM

    Is there a way to capture revision history in each drawing file's properties so that it updates when a title block update is initiated? If possible I would also like to use the same information to create a Master Change Table that lists all of the revision history that is updated from the same information in each drawing's properties. Please let me know if there is anyway to do this.

    Please use plain text.
    *Expert Elite*
    Posts: 975
    Registered: ‎03-09-2004

    Re: Revision history for each drawing

    11-28-2012 01:44 PM in reply to: gjarus

    AFAIK Autocad Electrical does not have this capability. I was looking into Vault which seems to provide this function but have not done enough research yet to say Yes for sure.

     

    I thought it would be nice if we had more DESC values instead of just 3 per drawing. These possibly be used for this function.

    Bob Hanrahan
    Ace User since 1998
    Please use plain text.
    *Expert Elite*
    cbenner
    Posts: 1,596
    Registered: ‎04-06-2010

    Re: Revision history for each drawing

    12-03-2012 11:55 AM in reply to: testsubject

    Vault can do this.  But in Electrical the Revision value lives at the project level.  So what I've done is create a custom property in Vault called "Revision Level".  I then mapped the "Revision" value from the Electrical project, to this custom property in the drawings.  Then in my titleblock revision section, I inserted a field mapped to "Revision Level".  So if the revision of the Project is bumped in Vault, it should trickle down to the drawings and populate that field in the titleblock.

     

    I've also got the Vault Revision Table on my drawings,... but as of today I am having some major issues with that so I can;t tell you it's wonderful yet.  Seems to have some stability issues.

    ChrisB

    Please use Mark Solutions!.Accept as Solution &Give Kudos!Kudos to further enhance the value of these forums. Thank you! :smileyhappy:


          

    Please use plain text.
    *Expert Elite*
    Posts: 975
    Registered: ‎03-09-2004

    Re: Revision history for each drawing

    12-03-2012 12:53 PM in reply to: cbenner

    Chris,

     

    How do you handle multiple rev history on a drawing? I have seen as many as 4 rev lines on some drawings and these need to be updated as well.

    Bob Hanrahan
    Ace User since 1998
    Please use plain text.
    *Expert Elite*
    cbenner
    Posts: 1,596
    Registered: ‎04-06-2010

    Re: Revision history for each drawing

    12-06-2012 04:48 AM in reply to: testsubject

    Well,... when the Vault Revision table was actually working.. (it quit on me a few days ago.. Adesk looking into it), the table would reflect whatever revisions exist in the Vault as a Released state.  You could set it to refresh the entire table or just update the latest revision.

     

    The challenge I've noted, and this has been brought to the attention of developers, is that at the Electrical Project level, you can only map the base revision property in Vault to the Item Master... not the file.  Unfortunately the Vault Revision table uses the Revision value from the file!  Hence the need for a UDP that maps from the Project revision in the Item Master, to the UDP in the drawing files.  Bit of a workaround but once it's set up it's not bad.

     

    Now they just need to fix the bug with the revision tables....

    ChrisB

    Please use Mark Solutions!.Accept as Solution &Give Kudos!Kudos to further enhance the value of these forums. Thank you! :smileyhappy:


          

    Please use plain text.
    Valued Contributor
    Nata_ly
    Posts: 76
    Registered: ‎08-21-2012

    Re: Revision history for each drawing

    01-03-2013 11:23 PM in reply to: cbenner

    I am very interested in this issue. How to withdraw the revision number on the drawing? Chris, I read your post but did not understand exactly how you pulled it off. Could you explain, please? :smileysad:

    Please use plain text.
    Distinguished Mentor
    Posts: 703
    Registered: ‎06-01-2010

    Re: Revision history for each drawing

    01-20-2013 05:44 PM in reply to: Nata_ly

    What is your definition of a Revision History for a dwg?

     

    When I revise a dwg, I usually add a small description of changes made as well as the new revision number to each dwg in a designated area. I have room for a number of these revision on each dwg and these to me would be the revision history for each dwg.

     

    See the attached jpg for an example from a recent dwg.

     

    Regards Brad

    Icemanau (NNTP handle: Brad Coleman)
    You may recognize me from the
    hundreds of previous newsreader posts
    I've made over the last 5 years
    as Brad Coleman

    Please use plain text.
    Valued Contributor
    Nata_ly
    Posts: 76
    Registered: ‎08-21-2012

    Re: Revision history for each drawing

    01-21-2013 12:28 AM in reply to: Icemanau

    Brad,

    I just want it to be automatically.

     

    For example, as in the Inventor there is a special command. It's available only for active Vault-type project and if you've connected to the Vault storage holds.

    The command creates the drawing table object with specific characteristics - product revision number, comment, and other cell values. They are updated automatically when you've changed the corresponding properties Vault Element associated with the drawing.

    (I hope I could explain it clear, more or less)

     

    So I want something similar in Electrical. Is there any command or attribute for this purpose?