why did defined wire sequence not affect the from/to report?

6 REPLIES 6
Reply
Message 1 of 7
Anonymous
234 Views, 6 Replies

why did defined wire sequence not affect the from/to report?

Hello,
In my schematic,the following devices included:
1 terminal block,TB1-1, in the drawing 1,
3 push buttons,-PB1,-PB2,-PB3, in drawing2,
3 other push buttons,-PB4,-PB5,-PB6 in drawing3.

For some reason,I dont want to modify the shematic.
Now, I want to define the wire sequence as follow:
TB1 - PB1- PB4 - PB2 - PB5 - PB3 - PB6.
who can tell me the method?
I have used the Define Wire Sequence Tool,but it seemed not to work fine.
the attachments are drawing1-3.
Any help is precaiated.

Regards.
6 REPLIES 6
Message 2 of 7
Anonymous
in reply to: Anonymous

drawing2
Message 3 of 7
Anonymous
in reply to: Anonymous

drawing3
Message 4 of 7
Anonymous
in reply to: Anonymous

Oh,sorry,my version is ACE2008.
Message 5 of 7
svend007
in reply to: Anonymous

I've looked at your drgs and it seems the report is correctly reporting your Schematic wire sequencing, (see attached image). To change the order, in this case, it's probably easiest to move items up or down within the 'Edit Wire Connection Sequence' dialog box to match your requirements.
Pete B.
Message 6 of 7
Anonymous
in reply to: Anonymous

Thanks for your help!
But in my ACE, i can not get the report as your attached image. Maybe it is the different version or the patch needed?
Message 7 of 7
svend007
in reply to: Anonymous

Yes, I think the AcadE 2008 Hotfix can/does help with sequencing problems.