    02-08-2013 11:13 AM

    I have recieved a survey and I am now ready to begin my design. BUT, when I try and create a "pipe network", I am unable to connect the plan view with the profile. I have everything on both the plan and profile (water, sanny, gas, cuvlerts, etc etc) which was provided by the surveyor. So overall I know C3D can do this very quick, but I just need help how it is not working in my favor!! Hopefully that was clear enough, happy Friday!

     

    The question in short: How to modify pipe network into an existing survey to transpose/connect in profile and plan views.

    Please use plain text.
    Valued Mentor
    Posts: 277
    Registered: ‎09-23-2008

    Re: implementing a new survey to begin storm pipe design

    02-08-2013 11:41 AM in reply to: tmactom

    The typical workflow is to draw the pipe network in the plan view and then add the parts to the profile view. Right click on on of the newly-drawn parts and look for "add to profile view' (one of many methods)

    Please use plain text.
    Contributor
    Posts: 13
    Registered: ‎02-01-2013

    Re: implementing a new survey to begin storm pipe design

    02-08-2013 12:30 PM in reply to: KirkNoonan

    Thanks for the reply. When I do that it still says "_AeccAddNetworkPartsToProf No profile views available." Yet I have a profile already in their. So I am a tad confused!

    Please use plain text.
    Valued Mentor
    Posts: 277
    Registered: ‎09-23-2008

    Re: implementing a new survey to begin storm pipe design

    02-08-2013 12:43 PM in reply to: tmactom
    Is your profile view really a profile view, or has it been exploded?
    Please use plain text.
    Contributor
    Posts: 13
    Registered: ‎02-01-2013

    Re: implementing a new survey to begin storm pipe design

    02-08-2013 12:52 PM in reply to: KirkNoonan

    Definitely exploded. Anything I can do to fix this? Or any options you may suggest. I recieved this survey so I have no idea how the consultant came about certain tasks.

    Please use plain text.
    Valued Mentor
    Posts: 277
    Registered: ‎09-23-2008

    Re: implementing a new survey to begin storm pipe design

    02-08-2013 01:13 PM in reply to: tmactom
    Look in your tool space to see if the profile still exists and recreate the profile view if it does. Otherwise, you can make a profile view on top of the exploded profile view and put your stuff in that one. Your view can be just a line on a no plot layer so that it doesn't interfere with the other one