Hello,
From what I have red the runout is considered the length required to transition the outside lane of the roadway from normal crown to zero cross slope. In Civil 3D this length is the transition length {t} from the transition length tables. The problem is that my country's standard specifies that on this transition length the curve has to go from normal crown to reverse crown and on the length of the spiral(runoff) from reverse crown to full superelevation i.e.
NCtoRC ---> {t}
RCtoFS ---> {l}
However these transitions don't exist in Civil 3D. Is there any solution for this problem?
Thank you in advance,
Bogdan
Re: Question regarding supereleva tion runout and runoff
Options
- Mark as New
- Bookmark
- Subscribe
- Subscribe to RSS Feed
- Highlight
- Email to a Friend
- Report Inappropriate Content
02-01-2012 03:50 AM in reply to:
bogdim2003
Try to apply xml in the attached file and give me a feedback.
It will gonna work with you.