    Hi

     

    I was wanting to know how people deal with multpile revisions of one sheet with sheetset manager, basically I want the cover sheet of drawings to have a list of drawings including the revision letter and revision date and on each individual sheet keep track of historical revisions 

     

    There is the current sheet revision and date fields.Does everyone usually just update these and manually keep track of historical revisions else where in there title block?.

     

     

    Regards

    Justin Ralston
    http://c3dxtreme.blogspot.com/
    Please use plain text.
    Product Support
    Posts: 709
    Registered: ‎02-08-2010

    Re: Multpile Revisions on one Sheet and SheetSet Manager

    11-13-2012 07:59 AM in reply to: ralstogj

    Although I cannot offer a perspective of a production environment, I do not think there is any automated way to accomplish this. If anything I hope this reply brings this topic to the top of the list to drum up some responses from users who may have encountered this.



    Seth Hall
    Product Support
    GCSO - CSS - FTS
    Autodesk, Inc.


    Being Civil
    Being Civil Twitter
    Being Civil Facebook







    Please use plain text.
    *Expert Elite*
    Joe-Bouza
    Posts: 3,307
    Registered: ‎12-15-2008

    Re: Multpile Revisions on one Sheet and SheetSet Manager

    11-13-2012 08:15 AM in reply to: ralstogj

    You would need to add custom fields into SSM to take the input per sheet revision. Although this creates a conundrum? how many revision fields do I need? If I make a provision for say six revision I'm sure I'll need seven in practice.

     

    So create as many custom revision fields you anticpate and place empty placeholders on the TB.

    Thank you

    Joseph D. Bouza, P.E. (one of 'THOSE' People) Civil 3D 2012 & 2013
    HP Z210 Workstation
    Intel Xeon CPU E31240 @ 3.30 Hz
    12 GB Ram

    Note: Its all Resistentialism, so keep calm and carry on


    64 Bit Win7 OS
    Please use plain text.
    Product Support
    Posts: 709
    Registered: ‎02-08-2010

    Re: Multpile Revisions on one Sheet and SheetSet Manager

    11-13-2012 08:18 AM in reply to: Joe-Bouza

    Thanks Joe!!



    Seth Hall
    Product Support
    GCSO - CSS - FTS
    Autodesk, Inc.


    Being Civil
    Being Civil Twitter
    Being Civil Facebook







    Please use plain text.
    *Expert Elite*
    Joe-Bouza
    Posts: 3,307
    Registered: ‎12-15-2008

    Re: Multpile Revisions on one Sheet and SheetSet Manager

    11-13-2012 08:20 AM in reply to: SethHall

    Hi Seth

     

    UBETCHA!

     

    I'll try to contribute more as time permits. :smileyvery-happy:

    Thank you

    Joseph D. Bouza, P.E. (one of 'THOSE' People) Civil 3D 2012 & 2013
    HP Z210 Workstation
    Intel Xeon CPU E31240 @ 3.30 Hz
    12 GB Ram

    Note: Its all Resistentialism, so keep calm and carry on


    64 Bit Win7 OS
    Please use plain text.
    Valued Mentor
    Posts: 470
    Registered: ‎09-29-2008

    Re: Multpile Revisions on one Sheet and SheetSet Manager

    11-13-2012 08:21 AM in reply to: ralstogj

    I have just been looking at the same thing. We would state the revisions on the sheet but oviously you cant have differing revisions with ease.

     

    I sudgest you could set up a custom sheet value for the current revision number and decriptive text which can be set by the user when he updates the drawing revision.

     

    This field must not be included in the revision text on the drawing, that should be plain Mtext otherwise you will get duplicate revisions anotated but could be projected to the master revision sheet you spoke of for record tracking.

     

     

     

     

     

     

     

    Please use plain text.
    Valued Mentor
    Posts: 549
    Registered: ‎10-01-2006

    Re: Multpile Revisions on one Sheet and SheetSet Manager

    11-13-2012 12:08 PM in reply to: ralstogj

    Sort of as Mike suggested I have put in the current revision field and that has to be updated by the user and the old revsion date and number added to the titile block. These are not custom fields at this stage in SSM that I can get the data for. As for the amount of revisions depends on the client one has been know to go through 26 letters it would be good if SSM could kind track of which one is the latest automatically and keep and auto extandable list of the historical ones so a complete drawing history could be printed from SSMtitileblock.png

    Regards