1.
Is the best way to create a design surface having a feature lines and then creating grading objects?
Then how do i create a FILL grading group for an eroded embankment of a reservoir. The examples on a typical book eg."master civil 3d 2012" shows a pond design.
I started a polyline boundary area just a bit smaller than cogo points consist of - surveypoints shot on the edge on the cliff, shot midway to wall of the cliff and shots taken to where the toe of rip rap fill-boundary should be.More points were created with elevations which represent whats on the site. (See image) . is this correct?
On the base feature boundary, do i just tell what lenght of the boundary line it must be graded from the top of the cliff, 1:2 slope and when I get to the portion of the base feature bounary line at the toe , I just tell how far the length of the boundary line is the and give a slope value of 1:1.5. Should this work
2. I'm about to try to model the the design surface a different way. (from the cliff 1:2, it goes this way for 5 ft, changes to 1:1.5)
do I create feature lines at toe , then vertical feature line between the toe and the cliff , then use the grading editor or elevation editor
3. Once I obtain the infill surface of the fill, how rotate or orient the model , ( rock material - rendered) so Photo 3 is draped over it.?
Thanks again.
Re: Grading Fill on a collapse embankment - a reposting
- Mark as New
- Bookmark
- Subscribe
- Subscribe to RSS Feed
- Highlight
- Email to a Friend
- Report Inappropriate Content
I think you would benefit greatly by hiring a Civil 3D specialist in your area to come out and help you for half-a-day.
Delta Engineering Systems
Redding, CA
Autodesk Authorized Value-Added Reseller
Re: Grading Fill on a collapse embankment - a reposting
- Mark as New
- Bookmark
- Subscribe
- Subscribe to RSS Feed
- Highlight
- Email to a Friend
- Report Inappropriate Content
You are very kind
Joseph D. Bouza, P.E. (one of 'THOSE' People) Civil 3D 2012 & 2013