1 or 2 corridors: How would you do this?
- Mark as New
- Bookmark
- Subscribe
- Subscribe to RSS Feed
- Highlight
- Email to a Friend
- Report Inappropriate Content
1 or 2 corridors: How would you do this?
I'm doing a street corridor design. There's a railroad crossing right in the middle. We are not redoing the railroad crossing. It is being left "as is".
Would you do 2 separate corridors, one on each side of the railroad crossing?
Or, would you do a single corridor, with a blank space in the middle where the railroad crossing is?
I'm leaning to 2 separate corridors, but am open to ideas. Thanks.
8GB RAM
AutoCAD Civil 3D 2013
Re: 1 or 2 corridors: How would you do this?
- Mark as New
- Bookmark
- Subscribe
- Subscribe to RSS Feed
- Highlight
- Email to a Friend
- Report Inappropriate Content
I would do one and hide the region at the tracks. This would eleiminate coordinating two PGL's
Joseph D. Bouza, P.E. (one of 'THOSE' People) Civil 3D 2012 & 2013
HP Z210 Workstation
Intel Xeon CPU E31240 @ 3.30 Hz
12 GB Ram
Note: Its all Resistentialism, so keep calm and carry on

64 Bit Win7 OS
Re: 1 or 2 corridors: How would you do this?
- Mark as New
- Bookmark
- Subscribe
- Subscribe to RSS Feed
- Highlight
- Email to a Friend
- Report Inappropriate Content
I would use 1 corridor with a gap at the tracks. Be sure to add a gap into the earthworks as well so that you don't have the volumes carry across the tracks.
I might use 2 corridors if I needed to have a second person work on the project and the track would be the split for the work load.
Cheers,
Peter Funk
Autodesk, Inc.

Peter Funk
Autodesk, Inc.